Pages

Sunday, March 10, 2013

STEP By STEP With PRIMAVERA - Part I

1. Setting up EPS;

2. Setting up OBS

3. Setting up Currency;
4. Setting up Unit;
5. Setting up Calendars;

6. Creating New Project File;
•File>New.
•ChooseEPSwheretheprojectwillbedeveloped.
•DetermineIDandtheNewProjectName;
•DetermineStartingDateofProject;
•DeterminetheResponsibleManager;
•Chooseratetype;
•ChooseNo,donotruntheProjectArchitect.
•Finish.

7. Setting up Project Information;

Setting up Work Break Down Structure (WBS);



8. Setting up Activity Code;

9. Adding Activities;
i.e. Activity name, activity code, duration, activity id


10. Setting Up Timescale;

11. Adding Milestone Activities;

12. Assign Activities Relationship;

13. Updating and Managing the Schedule ;

14. Schedule of Project Ready;